The Grahame Park regeneration - stay up to date

What's happening now

Notting Hill Genesis (NHG) have been working in partnership with the London Borough of Barnet to bring forward the regeneration of Grahame Park. In 2020 Barnet Council approved the outline planning application for the regeneration of Grahame Park and the concourse. This determined the total number of new homes as well as the building heights and sizes. 

Since then, we have started to build the first new affordable homes, known as Plot A, which are due to complete early in the new year.

Earlier this year we were successful in receiving detailed planning consent for the next phase, known as Plots K & H, which are in the area to the South of the Concourse and which we are planning to commence construction in late 2024.

To ensure that NHG can keep momentum, we have now started to progress the detailed design of an additional three plots and aim to submit a detailed planning application (also known as a Reserved Matters Application) in early 2024.

This application will include about 450 new homes, a replacement Nursery, Children’s Centre and new retail spaces along Bristol Avenue. 

We are keen to get residents feedback and will be holding a series of engagement days with you over the coming months so watch this space.

You can also submit your questions/thoughts/comments about the scheme – by emailing heybournepark@nhg.org.uk.

Consultation boards

Below you can view the current and previous consultation boards for the Grahame Park regeneration.

RMA2 consultation boards - October 2023

Here is the latest update on our plans for the next stage of the Grahame Park regeneration.

It includes a review of the progress we’re making to regenerate Grahame Park and a reminder of the approved masterplan and principles for change.

Below you can view and download our updated boards for the RMA2 consultation - October 2023. 

RMA2 consultation boards - July 2023

This is a reminder of the masterplan along with an update on site progress. We have an introduction to the second RMA, take a look at non-residential elements as well as the landscape being provided in Plots G, J and L.

Below you can view and download our updated boards for the RMA2 consultation - July 2023.

Plot 9 consultation boards

Take a look at our plans for plot 9 – the area just opposite the council building on the corner of Grahame Park Way and Bristol Avenue. The proposal is to build a welcoming space for residents and visitors to enjoy a coffee, discover more about the regeneration and showcase the new homes and facilities, as well as allowing space for community and enterprise activities and events. The building will be no more than two storeys, will include a landscaped area and is expected to be on the site for around 10 years to be a key focal point for the next stage of the regeneration.

 

December 2021: Phasing, Public realm and landscape, the Community Centre, Design of Plots H&K buildings

September 2021: Phasing, Public realm and landscape, the Community Centre

August 2021: Reminder of the masterplan, introduction to the area of focus for the first RMA, non-residential elements and landscape being provided in Plots H&K

July 2019: Grahame Park summer festival Final exhibition prior to the submission of the planning application. Summary of masterplan and phase 1 proposals.

May 2019: Phasing, transport, sustainability, choice of homes, appearance of Phase 1, Non-residential uses in the masterplan

March 2019: Introduction to the new project team and our goals for the regeneration