This dedicated section is where you can find the latest information on the Mildmay scheme in Tower Hamlets.
Appold Court: Update on the structural assessment - 27/10/2026
Our appointed structural engineers, Pell Frischmann, have identified minor cracking in two areas of the concrete structure at ground-floor level at Appold Court and have recommended further investigation and temporary supports.
The engineers’ current advice is that there is no reason for residents to move out. However, they have recommended installing temporary supports as soon as practicable while they investigate further. We have asked them to design these supports, and are arranging for a contractor to install them.
The engineers first reviewed the original construction drawings and calculations. This identified four areas of the ground-floor concrete slab that they wanted to inspect. This part of the structure is known as a “transfer slab” and helps support the building above.
During their planned inspection on 22 October, carried out largely from the underground car park, they found no signs of structural stress in two of these areas. In the other two, they found minor cracking that needs further investigation.
The investigation is not yet complete. The engineers need to carry out further checks and calculations to understand the significance of the cracking and whether any permanent work is needed.
The engineers have recommended temporary vertical supports, also known as propping, at the two locations as a precaution while their investigations continue. These are intended to provide additional support to the affected areas.
We do not yet have a confirmed installation date. We will let you know the arrangements, including any effect on parking, access or use of communal areas, as soon as these are confirmed.
Update on other buildings across the estate
Blacklock Court — Block C: As previously reported, we have received the structural assessment. The findings include recommendations for day-to-day building management and requests for further information on some of the original structural calculations.
Burbage Court — Block D: We have now received Pell Frischmann’s structural assessment. Its findings are similar to those for Blacklock Court. It identifies some day-to-day building management issues, which have been passed to the relevant teams for action. The engineers have also requested further information from the original structural engineers about some of their calculations.
Giles and Clements Courts — Blocks A and B: We are still awaiting the structural assessment reports and will share the findings and any next steps once these are available.
Bailey Court — Block G: We are still awaiting the structural assessment report. The engineers have assessed this block as very low risk because of its small size and simple construction. We will share the report’s findings once it is received.
Each building is being assessed individually. Findings at one building do not, on their own, establish the position at another.
Mildmay building investigations update - 30/09/2026
We have made good progress with the structural investigations across Mildmay and have now received the final engineer's report for Blacklock Court.
The report confirms that only a small number of recommendations have been identified, which will be incorporated into future maintenance and cyclical works alongside some final building checks. No significant structural concerns have been identified.
Investigations across the remaining blocks are continuing to progress well. Site visits have now been completed for a number of buildings, and we are awaiting final reports for Giles Court (Block B), Burbage Court, Clement Court, Bailey Court, the church and Giles Court (Block A). Work at Appold Court is also progressing, with further site visits planned in October.
Resident safety remains our highest priority. The structural engineers continue to advise that residents are safe in their homes and that nothing has been identified which poses a risk to residents.
We will provide a further update once the remaining reports have been received, with our next update due by the end of October.
Mildmay update - 15/07/2026
We’re letting residents and home owners know that the original structural engineers for Mildmay have identified potential issues with the design of Blacklock Court (Block C) and an area of Giles Court and Clements Court (Block B) this is shown on the plan below.

These potential issues were flagged in a desk-based review and relate to the original structural design of the Mildmay scheme, they are not based on any recorded concerns regarding the performance or actual condition of the buildings.
The original structural engineers have provided assurance that they have not identified anything at this stage that poses a risk to residents and this has been confirmed by our own independent structural engineers.
Frequently asked questions (FAQs)
No potential structural issues have been identified in Burbage Court (shown as Block D on the plan), some homes in Giles Court (Block A on the plan) and Bailey Court (Block G).
The original structural engineers have not yet assessed Appold Court & Godfrey Place (Block E on the plan) yet. We at NHG have already instructed an independent structural assessment for this building and the desktop assessment is progressing but not yet complete. We will update on this as soon as we have more information.
Resident safety remains our number one priority and we will continue to prioritise this. Please be assured if there is any suggestion of risk to residents, we will be in touch and take all necessary precautionary action as quickly as possible.
The independent structural engineers will undertake some further investigations and to provide further assurance we are also planning to undertake some structural assessments of our own across all blocks on the development. These will extend beyond areas of potential concern raised by the original structural engineers and will look at the actual condition of all buildings.
The investigations will include visual inspections of the exterior, communal areas and inside a small number of homes. There are no plans for any invasive inspections at the current time. If we would like access into your home we will contact you directly.
We appreciate this news may be concerning, but we wanted to ensure that we are open with you and sharing information about matters that may affect your home. We understand you may have questions and we do want to hear them, so you can ask these using the form below.
We don’t have all the answers just yet, but we are in the process of getting them and are committed to updating you again by mid-August.